Transfer line and irrigation and downstream drainage sub-network P3 , P9 of Robat Karim Plaint

Agreement Specifications:

Project Name    : Transfer line and irrigation and downstream drainage sub-network P3 , P9 of Robat Karim Plaint 

Contract No.             : 101/20/86353

Contract Date            : Feb.19, 2008

Contract Duration     : 18 months

Initial Agreement Price      : Rls. 13,483,000,000/- equal to USD 4704466

Project Site                : Robat Karim Plaint 

Contractor's Name     : Water and Soil Engineering Services Company 

Employer's Particulars:

Employer's Name       : Tehran province Agriculture Jihad Org.   

Employer's Address    : Seyed Jamaleddin Asadabadi St., Tehran province Agriculture Jihad Org.

Consultant's Particulars:

Name of Consultant Engineers Co.: Lar Consultant Engineers Co.

Consultant's Address : No. 23, Bradaran Sharifi St., After Vanak Sq., Valiasr Ave., Tehran, Iran

Main Volumes of Work Based on Initial Volumes of Agreement:

Summary of Work      : - Purchase of asbestos and execution of water transfer pipe in downstream lands

- Purchase of polyethylene pipe and execution of irrigation sub-network in downstream lands of P8 and P9 basin

- Purchase of related valves and fittings, installation of them

- Construction of surface drains

- Construction of pipeline route structures and drains

- Execution of service roads of pipeline route structures and drains 

Earth filling volume           : 27215 m3

Excavation volume            : 24157 m3

Bar                           : 153213 kg.

Concrete Work                   : 1720 m3

Base and Sub-base             :

Binder and Topeka asphalt : 96000 Sqm. Binder asphalt & 64000 Sqm. Topeka asphalt 

Signed:

Contractor's Representatives: Mr. Mehdi Varshabi & Mr. Seyed Alireza Shariat Panahi

Employer's Representative: Mr. Seyed Hossein Mohseni