Agreement Specifications:

Project Name    : Execution of reservoir dam of Ziba Mohammad and affiliated installations  

Contract No.             : 1437/800

Contract Date            : May 4, 2013

Contract Duration     : 42 months

Initial Agreement Price      : Rls. 194,753,000,000/- equal to USD 24,968,333

Project Site                : 30 Km of Khorramabad

Contractor's Name     : Water and Soil Engineering Services Company 

Employer's Particulars:

Employer's Name       : Lorestan Regional Water Joint Stock Company

Employer's Address    : Valiasr St., Lorestan Regional Water Joint Stock Company, Khorramabad, Iran

Website             : www.lsrw.ir

Tel and Fax              : 3224023-3206020

Consultant's Particulars:

Name of Consultant Engineers Co.: Ab Ara Sazeh Consultant Engineers Co.

Consultant's Address : No. 19, Arabi Shahid Alley, Sanaei St., Karim Khan Blvd., Tehran, Iran

Tel. and Fax              : 88829054- 8823996

Main Volumes of Work Based on Initial Volumes of Agreement:

Summary of Work      : - Provisional diversion system

- Reservoir dam , - weir, basin, deep discharger system , - Access roads,

- Hydromechanical equipment and instrumentation, - Maintenance and operation buildings, landscaping and lighting   

Earth filling volume   : 922400 m3

Excavation volume    : 326590 m3

Bar                   : 644750 kg.

Concrete Work           : 6390 m3

Base and Sub-base     :- 

Signed:

Contractor's Representatives: Mr. Abbas Zareh and Mr. Mr. Seyed Alireza Shariat Panahi