Agreement Specifications:
Project Name : Construction of Bahreh new
floodway from Changiz Bridge to Bridge of Ahvaz-Abadan Rd.
Contract
No. :
Contract
Date :
Contract Duration : 18 months
Initial Agreement Price :
Rls. 36,653,100,000/-
Project
Site
: Ahvaz-Abadan Rd.
Contractor's Name : Water and
Soil Engineering Services Company
Employer's Particulars:
Employer's Name :
Khuzestan Water and Electricity Org.
Employer's Address : 5-Floor. Bldg., Golestan
Crossroads, Ahvaz, Iran
Website
:
Consultant's Particulars:
Name of Consultant Engineers Co.: Saz Ab Pardazan
Consultant Engineers Co.
Consultant's Address : Corner of West Nahid St., Golestan Blvd., Iran
Tel. and
Fax
:
Email
:
Main Volumes of Work Based on Initial Volumes of
Agreement:
Summary of Work :
-Removal of Bush, earth filling, sludge removal, excavation, land leveling and
regulation, reinforcement, concrete work, dieing, steel works, asphalt
concrete, steel pipe, polyethylene and other cases predicted in documents of
agreement.
Earth filling volume : 146434 m3
Excavation volume : 933700 m3
Bar
: 123346 kg.
Concrete
Work : 1427 m3
Base and Sub-base :
Signed:
Contractor's Representatives: Mr. Behzadipour and Mr.
Shariat Panahi
Employer's Representatives: Mr. Ebrahimzadeh and Mr.
Moradi
Agreement Specifications:
Project Name : Construction of Second Runway of 3rd lot
of Bostanabad-Sarab
Contract
No. :
91/11063
Contract
Date : June
13, 2011
Contract Duration : 20 months
Initial Agreement Price :
Rls. 68,221,713,900/- equal to USD 13,641,614
Project
Site
: Bostanabad-Sarab
Contractor's Name : Water and
Soil Engineering Services Company
Employer's Particulars:
Employer's Name :
East Azerbaijan Province Road & Transportation Dept. Gen.
Employer's Address : Railway Sq.,
East Azerbaijan Province Road & Transportation Dept. Gen., Tabriz, Iran.
Website
: 4651011-5
Email
:
Tel and
Fax
:
Consultant's Particulars:
Name of Consultant Engineers : -
Consultant's Address :
Tel. and
Fax
:
Website
:
Main Volumes of Work Based on Initial Volumes of
Agreement:
Summary of Work :
Construction of (earth dam, technical buildings, base and sub-base, binder
asphalt, Topeka asphalt), second runway of third lot of Bostanabad – Sarab as
per attached and notified map and specifications and issue 101 of Management
and Planning Org.
Earth filling
volume : 229327 m3
Excavation
volume :
300658 m3
Bar
: 141261 kg.
Concrete
Work
: 2546 m3
Base and
Sub-base
: 165255 m3
Binder and Topeka asphalt : 423760 kg.
Signed:
Contractor's Representatives: Mr. Nazari & Mr.
Shariat Panahi
Employer's Representative: Mr. Alizadeh